The datasheet is available via this link.
| Nr. | Item | Quantity |
|---|---|---|
| 1 | Octave Edgebox Controller | 1 |
| 2 | 24V DC Supply | 1 |
| 3 | 24V DC cable (red/black) | 1 |

Octave Edgebox Controller (left), 24V DC Supply (center) and 24V DC cable (right)

Alternatively, a 24V AC/DC adapter can be provided (center) with a Female connector (right)

Connection Schematic of the Octave Edgebox
To install the EdgeBox on site:
A power meter is required on the grid connection of the site. The metering granularity must be real-time, not quarter-hourly.
The power meter must have Modbus TCP/IP connectivity.
<aside> 💡
Configuration of the site meter
The site meter must be configured correctly, and you should verify that it accurately reads the site's power consumption.
Please verify the wiring and configuration of the current sensors.
</aside>
The preferred sign convention is as follows: